PM Construction & Rehab, LLC dba IPR South Central – ITB: Certified MBE/WBE firms
Project: Wastewater Collection System Rehabilitation and Renewal – Project No.: WBS No. R-000266-0346-4, File No. 4235-118
Project Location: Houston, TX
Bid Due Date: 1/13/2022
Quotes Returned: 1/10/2022– 5:00 P.M. EST
Scopes:
- Clean/CCTV
- 6” – 48” Gravity and Sanitary sewer all depths
- Debris Collections, Removal, and Disposal
- Traffic Control Plan
- Traffic Control – Flaggers, Install Traffic Loop Detector
- Suppliers
- SDR 19 6” to 18” sizes
- HDPE 6” to 12” sizes
- Open Cut
- Diversion Pumping 6” – 8”
- Bypass piping 8” – 8”
- Well pointing/Dewatering
- Trench Safety plan
- Excavation by hand (Entry/Exit pits)
- Obstruction removal by excavation
- Point repairs
- Pipe replacement beyond point repairs 6” – 48“ all depths
- Abandonment of point repairs
- Cut or remove existing liners from host pipe
- Slurry Boring 8” – 12” up to 15’ Depths
- Reconnect Service connection by excavation, hand excavation
- Cement stabilized sand backfill
- Sliplining of existing Service line
- Abandonment of sanitary sewer
- Cleanout Sanitary sewer 4”, 6” and 12”
- Manhole adjustment new frame and covers
- Install 4’ – 8’ Dia. Manholes, concrete, fiberglass
- Remove and replace fencing, all materials
- Extra Excavation by Machine removal Cement stabilized sand/Concrete
- Manhole Rehab
- 1” Thick concrete liner
- Manhole inserts
- Benches and inverts
- Concrete
- Remove and replace 4-1/2” concrete sidewalk
- Remove and replace 6” concrete driveway
- Remove and replace 8” concrete pavement
- Remove and replace 8” to `10” Concrete Slab using 5000 psi High early Strength
- Remove and replace Curb and Gutter
- Asphalt
- Remove and replace 2” HMCA (type-D)
- Remove and replace semi-rigid base
- Milling of pavement
- Asphalt overlay 2” HMAC
- Saw joint
- Landscape
- Remove and replace trees
Specs/Plans – Jennifer Elder | [email protected] | 404-927-4603