PREMIER UNDERGROUND RENEWAL INFRASTRUCTURE SOLUTIONS

Project: 2023 CWSRF Sanitary Sewer Rehabilitation

Inliner Solutions, LLC – ITB: W/S/MBE Certified Firms

Project: 2023 CWSRF Sanitary Sewer Rehabilitation

Project Location: Eufaula, AL

Bid Due Date: June 18th, 2026

Quotes Returned: June 16th, 2026

Scopes:

  • 223 VF of Manhole Rehabilitation.
  • Open Cut work such as 8” Point Repairs and Sag Repairs
  • Install of 4,900 LF of 8” PVC Sewer Main
  • Core Drilling to connect existing Manholes
  • Lateral connections to Sewer Line
  • Manhole Ring and Cover Reset
  • Locate and raise existing Manholes
  • New 48” Dia Manhole with Ring and Cover
  • Excavation and Restoration
  • Concrete Curb and Gutter Removal and Disposal
  • Clearing, Grubbing and Erosion control
  • Sewer Clean/CCTV

Specs/Plans/Questions– Ashden Middlebrooks | ashden.middlebrooks@puriscorp.com | 470-503-5624