Project: Culvert Rehabilitation
Project Location: Corinth, MS
Bid Due Date: 07/15/2025
Quotes Returned: 07/10/2025
Scopes:
- Remove existing CMP pipe, dispose of off-site. Pipe is approximately 8’ diameter (roughly 98”).
- Case in place concrete headwall (2 total).
- Concrete form work – erecting & stripping
- Rebar installation/tying
- Concrete pour & finish
- Concrete supplier (truck to site)
- Rebar supplier (deliver to site)
- Rip Rap Installation (Size 300)
- Install geotextile (type V) and rip rap (size 300) per plans
- Supply rip rap (truck to site)
- Install & remove temporary construction entrance
- Install & remove temporary construction entrance
- Supply construction entrance aggregate (truck to site)
- Erosion Control
- Supply silt fence material, sandbags, sediment filter bag, temporary seed/straw, permanent seed/straw
- Install silt fence material, sandbags, sediment filter bag, temporary seed/straw, permanent seed/straw
- Restoration grading activities
- Finish grading
- Topsoil placement
- Supply topsoil (truck to site)
- Project sign
- Temporary dumpster service
- Portable toilet rental & service