Project: Long Quarter Sewershed Structural Rehabilitation South – Contract No. 21001 SX0

Inliner Solutions – ITB: MBE/WBE Certified Firms

Project: Long Quarter Sewershed Structural Rehabilitation South – Contract No. 21001 SX0

Project Location: Baltimore Co., MD

Bid Due Date: 01/25/2024

Quotes Returned: 01/22/2024

Scopes:

  • CCTV & Cleaning
  • Pre CIPP CCTV & Cleaning
  • Removal of protruding Taps
  • Lateral Rehabilitation
    • CIPP Spot Repairs
    • Service Lateral CIPP
    • Lateral lining
    • Grouting
    • Air Test Service connections
  • Mainline CIPP Point Repairs
    • 8” Spot Repairs
  • Open Cut Sewer
    • Point Repairs – Mainline
    • Cleanout installations
    • Lateral replacement
    • Drop connections
    • Raise MH to grade
  • Manhole Rehabilitation
    • Cementitious
    • Grout Injection/seal leaks
    • Replace Frame/Cover
    • Rebuild Bench/channel
  • Manhole Installation/Replacement
    • Precast
  • Traffic Control
    • Flaggers/Signs/Arrow boards; etc.
  • Landscaping
    • Seeding and Sodding, topsoil, supply and/or install of new trees
    • Site Grading (for restoration purposes)
    • Tree and Brush removal
  • Asphalt/Pavement Restoration
    • Alleys, roadways, sidewalks; etc.
    • Curb Inlet Replacement
    • Pavement Markings
  • Clearing & Grubbing
    • Tree Felling
    • Tree Protection
    • Root Pruning
    • Tree protection fence
  • Erosion/Sediment Control
    • Silt Fence/Super silt fence
  • Excavation/Access
    • Select Backfill
    • Temp Access Bridges
    • Stabilized Construction Entrance
    • Temp Mulch Access Roads
    • Geotextile
  • Misc.
    • Manhole Abandonment
    • Demo/removal of pipe

Specs/Plans /Questions– Ashden Middlebrooks | ashden.middlebrooks@puriscorp.com | 470-503-5624