PM Construction & Rehab, LLC dba IPR South Central – ITB: MBE/WBE/SBE/ Labor Surplus Area Firms
Project: Sanitary Sewer and Drainage Improvements on Dr. Martin Luther King Jr Drive
Project Location: Montgomery, Texas
Bid Due Date: 2/16/2022
Quotes Returned: 2/11/2022
Scopes:
LIST OF ACCEPTABLE BASE BID EQUIPMENT MANUFACTURERS
MANHOLE CEMENTIOUS GROUT
- Quadex
- Strong Seal-MS-2C
- Reliner MSP
- Permacast-MS-10,000
- Emaco S88-Ca/Re-006
CURED-IN-PLACE MANHOLE
- Triplex
Clean/CCTV
- 4214 LF of 8”
- Project report plan
- Remove Protruding taps
- Heavy Cleaning 8” pipe
- Root removal and other obstructions
Manhole Rehab
- Manhole Television inspection
- Rehab 48” Manhole, Sealing and CIPP structural liner
- Reshape & reseal Manhole bench and invert
- Rehab 48” manhole resetting and resealing ring and throat w/1” cementitious grout
- Grout and reseal lateral connection interior
- Grout exterior of manhole frame
- Cleaning Manhole
- Install infiltration dish Stainless Steel
Open Cut
- R&R 8” cleanouts
- R&R Manhole Ring and Lid
- 12”, 15”, and 24” Dual Reinforced Concrete Pipe
- 18” and 24” Reinforced Concrete pipe
- Excavation of ditch
- Install concrete slope
- Remove existing gravel driveway and replace with asphalt
- R&R existing asphalt pavement including culverts
- R&R existing concrete driveway and culverts
- 8” open cut repairs
- Service lead repair via open cut
- R&R 8’ SDR 26 PVC
Erosion Control
- Reinforced filter fabric barrier
Traffic Control
- Signs, cones, flaggers, arrow boards
Specs/Plans /Questions– Crystal Galvan | [email protected] | (678) 436-6814