IPR Northeast, LLC – ITB: M/SLBE Firms
Project: Area Water and Sewer House Connection Construction | Contract No. AC7368A22
Project Location: Montgomery and Prince Georges Counties, Maryland
Bid Due Date: 4-26-2022
Quotes Returned: 4-21-2022
Scopes:
Open Cut/Excavation
- Test Pits
- Gravel backfill
- Borrow trench backfill
- Crusher run
- Install New Meter Housing
- Abandon Existing Water House Connection
- Abandon Sewer House Connection
- Abandon Pressure Sewer House Connection
- 20,000 LF of 1-2” Water House Connection
- 2000 LF of 1-2” Water House Connection
- 3600 LF of 4-6” Sewer House Connection
- Service Valve Assembly
- Install 1.5 to 2” Water Service on 16” PCCP Main
- Install 1.5 to 2” Water Service on 24” PCCP Main
Erosion Control
- Silt Fence
- Straw bale dike
Paving
- Temporary HMAC to replace cold patch in State/Arterial Roads
Specs/Plans /Questions– Crystal Galvan | [email protected] | 678-436-6814