Inliner Solutions – ITB: MBE/WBE Certified Firms
Project: Long Quarter Sewershed Structural Rehabilitation South – Contract No. 21001 SX0
Project Location: Baltimore Co., MD
Bid Due Date: 01/25/2024
Quotes Returned: 01/22/2024
Scopes:
- CCTV & Cleaning
- Pre CIPP CCTV & Cleaning
- Removal of protruding Taps
- Lateral Rehabilitation
- CIPP Spot Repairs
- Service Lateral CIPP
- Lateral lining
- Grouting
- Air Test Service connections
- Mainline CIPP Point Repairs
- 8” Spot Repairs
- Open Cut Sewer
- Point Repairs – Mainline
- Cleanout installations
- Lateral replacement
- Drop connections
- Raise MH to grade
- Manhole Rehabilitation
- Cementitious
- Grout Injection/seal leaks
- Replace Frame/Cover
- Rebuild Bench/channel
- Manhole Installation/Replacement
- Precast
- Traffic Control
- Flaggers/Signs/Arrow boards; etc.
- Landscaping
- Seeding and Sodding, topsoil, supply and/or install of new trees
- Site Grading (for restoration purposes)
- Tree and Brush removal
- Asphalt/Pavement Restoration
- Alleys, roadways, sidewalks; etc.
- Curb Inlet Replacement
- Pavement Markings
- Clearing & Grubbing
- Tree Felling
- Tree Protection
- Root Pruning
- Tree protection fence
- Erosion/Sediment Control
- Silt Fence/Super silt fence
- Excavation/Access
- Select Backfill
- Temp Access Bridges
- Stabilized Construction Entrance
- Temp Mulch Access Roads
- Geotextile
- Misc.
- Manhole Abandonment
- Demo/removal of pipe
Specs/Plans /Questions– Ashden Middlebrooks | ashden.middlebrooks@puriscorp.com | 470-503-5624