PREMIER UNDERGROUND RENEWAL INFRASTRUCTURE SOLUTIONS

Project: CDBG East Of Wurzbach Sewer Main

PM Construction & Rehab, LLC – ITB: S/M/WBE & Section 3 Certified Firms

Project: CDBG East Of Wurzbach Sewer Main

Project Location: Leon Valley, TX

Bid Due Date: 12/05/2024

Quotes Returned: 12/02/2024

Scopes:

CCTV (562998)

  • Pre CCTV & Clean of Sanitary lines 8” 1,1199LF
  • Post CCTV with Inclinometer of lines 1,209LF

Bypass (237110)

  • Plan Set contain suggested bypass Plan.

Manhole rehab (237110)

  • 55VF: A combination of cementitious coatings followed by an approved epoxy coating.

Open cut (238910)

  • 10” point repairs on 8” sanitary lines – backfilled with flowable fill
  • Asphalt restoration

Traffic control (561990)

  • Traffic control for working areas eclosed in red lines

    Specs/Plans /Questions– Ashden Middlebrooks | [email protected] | 470-503-5624