PREMIER UNDERGROUND RENEWAL INFRASTRUCTURE SOLUTIONS

Project: DCW-SOL-23-10251 220160-Major Sewer Rehabilitation 1-5 Northeast Boundary

Project: DCW-SOL-23-10251 220160-Major Sewer Rehabilitation 1-5 Northeast Boundary

Project Location: Washington DC

Bid Due Date: May 11, 2023, at 11:00 AM

Quotes Returned: May 8, 2023, before 4:00 PM for Consideration and review

Scopes:

Inliner Solutions, LLC, is seeking subcontractors to provide the following, but not limited to, services for the project listed above:

  • CCTV & Cleaning
  • Erosion
  • Sediment Control
  • Traffic Control
  • Landscaping
  • Temporary Road Construction
  • Large Bypass System/Flow Control
  • Misc. Dig Work as needed
  • Scaffolding Supplier

Project Specifics

The majority of the assets will be rehabilitated using trenchless rehabilitation technologies, primary Geopolymer Lining System (GLS). The work includes:

Structural rehabilitation using Geopolymer Lining System (GLS) on approximately nine hundred (900) linear feet of 22-foot circular and three hundred and seventy (370) linear feet of 6-foot by 9-foot combined sewer pipes with associated internal point repairs and lateral/pipe reinstatements.

Structural rehabilitation using Geopolymer Lining System (GLS) on five (5) sewer manholes/structures.

Internal sewer flow control, pipe cleaning, inspection, and erosion and sediment control of project site.

For further information regarding this Bid Opportunity please visit DC Water’s Procurement website: https://www.dcwater.com/procurement


Specs/Plans /Questions– Annastacia Tooke | Annastacia.Tooke@puriscorp.com | 980-448-1066