PM Construction & Rehab, LLC – ITB: M/W/SBE & Section 3 Certified Firms
Project: GLO SS Project 1 Sanitary Sewer Improvements
Project Location: Kingsville, TX
Bid Due Date: 04/09/2024
Quotes Returned: 04/04/2024
Scopes:
CCTV
- Pre CCTV CIPP lines 6”-18” of 7,477LF
- Post CCTV open cut lines 6” – 24” of 3,802LF
Manhole rehab
- Manhole Protective Coating (60Mil)
Bypass
- 6” sound attenuated diesel Pumps X 2 and layflat hose with Bauer fittings X 1000LF
- Bypass plans
Traffic control
- TX Dot double lane closures – up to 700 LF per.
- Setups to be moved daily.
- TX Dot traffic plans – engineered stamped
Open cut
- Asphalt pavement
- Concrete curb, ramp, sidewalk, driveway
- Gravel Driveway Repair
- Junction Box W/ Sanitary Sewer Crossing
- Re-Grade Ditch Area
- 4’Ø Fiberglass Sanitary Sewer Manhole
- 12”Ø Steel Casing Bore ¼” Thickness W/Pipe Vent
- 6ӯ Sanitary Sewer Line Pvc Sdr-26
- 18ӯ Sanitary Sewer Line Pvc Sdr-26
- 6ӯ Sanitary Sewer Force Main Line Pvc Dr-18 (C-900)
- 12ӯ Sanitary Sewer Line Pvc Dr-18 (C900)
- 24ӯ Rcp (Class V)
- Lift Station Assembly
- Generator (62.5 Kva) w/ Stand By Generator Concrete Pad
- Steel Canopy Structure
- Electrical System
- Aep Power Pole Transformer
Specs/Plans /Questions– Ashden Middlebrooks | [email protected] | 470-503-5624