Project: 2024 Sewer Pipe Bursting and Ancillary Infrastructure Improvements

PM Construction & Rehab, LLC – ITB: DBE & SBE Certified Firms

Project: 2024 Sewer Pipe Bursting and Ancillary Infrastructure Improvements

Project Location: Lake Charles, LA

Bid Due Date: 06/04/2024

Quotes Returned: 05/30/2024

Scopes:

Aggregate (423320)

  • #610 maintenance limestone 4,250 tons

Supply (326199)

  • Fiberglass manholes- riser rings
  • 8” & 15” HDPE DR 17 IPS w/ full circle clamps
  • 6″ diameter SDR-26 PVC pipe, fittings, saddle tees, couplings, meter box, clean-outs.

Hydro Seeding (561730)

  • 2,500 S.Y.

CCTV (562998)

  • Pre-Clean & CCTV and Post CCTV of lines 8” & 15 “ sanitary sewer lines, 5,779 LF

Traffic control LA DOTD (561990)

  • Single lane closures
  • Street closures/ traffic diversions
  • Junction closures

Paving (237310)

  • Furnish and install 4 inch thick plain concrete pavement for sidewalks
  • Furnish and install 6 inch thick reinforced concrete pavement for asphalt base, driveways – Type B
  • Furnish and install 8 inch thick reinforced concrete pavement for roadways – Type B
  • Furnish & install hot mix asphalt wearing course, 2 inch thick, incl. tack coat

Manhole rehab (237110)

  • Install multi-layered interior coating for sewer manholes, Spectrashield, Triple Shield, or approved equal

Bypass (237110)

  • Furnish and maintain whisper quiet temporary bypass pump, lines 8” & 15” sanitary sewer lines.

Specs/Plans /Questions– Ashden Middlebrooks | [email protected] | 470-503-5624